Skip to main content
Last reviewed: Next review due: Reflects current manufacturing performance bond requirements
2026 Requirements Verified
The Compliance Question

“My DLA contract requires a bond — which one, and why?”

Start with FAR 28.103-1(a): “Generally, agencies shall not require performance and payment bonds for other than construction contracts.” Supply contracts are bondless by default. A bond shows up on your manufacturing contract only when one of four enumerated trigger conditions in FAR 28.103-2 is in play — most often, when the government is advancing you cash before end-items ship. Get the trigger named in writing and you control the conversation about penal sum, form type, and whether a reduced penal sum (FAR Part 28 permits agency discretion for supply bonds) will satisfy the contracting officer.

Two regulatory branches, almost never cited correctly together

Manufacturing/supply contracts live under FAR 28.103 (permissive, trigger-based). Construction contracts live under the Miller Act, 40 U.S.C. 3131 ($100K threshold; $150K only for military construction under 10 U.S.C. 2852). Pages that quote “$150,000” as a universal federal performance bond floor are conflating two unrelated statutes.

FAR 28.103-2 — verbatim

Four trigger conditions force a bond onto a supply contract

These are the only conditions under which a manufacturing or supply contract over the $250,000 simplified acquisition threshold (FAR 2.101) can be made to carry a performance bond. Anything outside these four does not justify a bond requirement.

  1. 01

    Government property or funds in the contractor's hands

    Government property or funds are to be provided to the contractor for use in performing the contract or as partial compensation. Government-furnished property (GFP), government-furnished material (GFM), and certain CAS-covered cost transactions land here.

  2. 02

    Mid-contract asset sale, merger, or novation

    A contractor sells assets to or merges with another concern and the Government recognizes the successor in interest. The bond gives the agency assurance the successor can finish what the predecessor started.

  3. 03

    Substantial progress payments before end-item delivery

    Substantial progress payments are made before delivery of end items starts. This is the trigger that fires most often on DLA prime vendor and long-term agreements — the agency advances raw-material funds, the contractor produces, the government has cash exposure before the first pallet ships.

  4. 04

    Dismantling, demolition, or removal of improvements

    Contracts are for dismantling, demolition, or removal of improvements. Rare for primary manufacturers but routine for contractors who handle decommissioned equipment, salvage, or de-installation work.

Plus one ongoing-contract rule: FAR 28.103-2 also permits a contracting officer to require additional performance bond protection when a contract price is increased — an ongoing-contract protection, not a threshold trigger. Total enumerated conditions: four triggers plus one price-increase rule.

FAR 28.103
Supply contract bond rules
FAR 52.228-16
Other Than Construction clause
10 U.S.C. 4862
Berry Amendment (renumbered)
SBA up to $14M
Federal contract guarantee cap

Official Federal Requirements

"Generally, agencies shall not require performance and payment bonds for other than construction contracts. Performance and payment bonds may be used only as permitted in 28.103-2 and 28.103-3."
Federal Acquisition Regulation, Subpart 28.1FAR 28.103-1(a)

The corollary in FAR 28.103-1(c) is just as important once you are past contract award: “No bond shall be required after the contract has been awarded if it was not specifically required in the contract, except as may be determined necessary for a contract modification.” A contracting officer cannot quietly add a bond requirement after the fact — only a modification can.

A manufacturing supply bond is not a construction performance bond

Different statutory branch, different FAR clause, different standard form, different penal-sum default. Five rows that no competitor page lays side by side — and the table contracting officers and underwriters work from.

Defense Logistics Agency — the supply-bond context

How DLA layers on top of FAR Part 28

DLA has no standalone bond policy on dla.mil. DLA bond requirements derive entirely from FAR Part 28, DFARS Part 228, and the Defense Logistics Acquisition Directive (DLAD) Part 28 supplement — currently DLAD Revision 5, effective January 1, 2026. The DLAD adds one operationally important requirement.

Under DLAD 28.106-90, DLA contracting officers must obtain legal sufficiency review from the Office of Counsel on every bond and every consent of surety. This is not a rubber stamp — expect days, not hours, of processing on top of the underwriting timeline. A bond that would clear at a civilian agency in 48 hours can take a week through DLA legal review.

The bond trigger itself on DLA contracts almost always traces back to FAR 28.103-2(3) — substantial progress payments before delivery starts. DLA prime vendor contracts (subsistence, clothing, medical supply, industrial hardware) and Long-Term Agreements often advance cash to fund material buys. That advance is what creates the government exposure the bond is sized to cover. No separate DLA-specific dollar threshold or independent advance-payment bond rule exists — it is FAR 28.103-2(3) all the way through.

DLA bond timeline reality

Day ranges reflect typical DLA processing timelines — actual durations vary by contracting office and bond complexity.

  • Day 0: Award notice with bond clause (FAR 52.228-16) and form (SF 1418).
  • Day 1–5: Underwriting package to surety — YTD financials, work-on-hand, advance-payment schedule.
  • Day 5–8: Carrier approval, bond executed on SF 1418, power of attorney attached.
  • Day 8–14: DLA Office of Counsel legal sufficiency review (DLAD 28.106-90).
  • Day 14–21: Notice to proceed; first advance payment authorized (FAR 28.103-1(b)).
Berry-compliant supply chains underwrite better

Why an all-domestic supply chain gets you a lower bond rate

The Berry Amendment — now codified at 10 U.S.C. 4862 after being renumbered from 10 U.S.C. 2533a by Public Law 116-283 (FY2021 NDAA, effective January 1, 2022) — requires DoD funds to be spent on covered articles that are grown, reprocessed, reused, or produced in the United States. Covered articles include food, clothing and textiles, tents and structural components, natural fibers, individual equipment (FSC 8465), stainless steel flatware, and dinnerware. Specialty metals are a separate statute (10 U.S.C. 4863) and a separate DFARS clause (252.225-7009).

The implementing contract clause is DFARS 252.225-7012 — Preference for Certain Domestic Commodities (APR 2022), prescribed by DFARS 225.7002-3 and required in solicitations and contracts, including FAR Part 12 commercial item contracts, unless an exception under DFARS 225.7002-2 applies.

The underwriting angle nobody else talks about: a Berry-compliant manufacturer is, by definition, sourcing covered inputs from inside the United States. No offshore raw-material lead times, no foreign port congestion risk, no FX exposure on incoming material. From the surety's side of the desk, that documented domestic supply chain reduces the probability of a delivery-default claim — which is what a supply performance bond is actually written to cover. The result is a better-priced bond — underwriters consistently quote lower rates for Berry-compliant contracts, though the exact spread varies by carrier, contract size, and credit profile — for the manufacturer who can hand the underwriter Berry compliance certifications, mill certs, and DFARS 252.225-7012 documentation up front.

Covered under 10 U.S.C. 4862 (Berry)

  • • Food
  • • Clothing, fabrics, yarns — cotton, wool, silk, synthetic
  • • Tents and structural components
  • • Individual equipment (Federal Supply Class 8465)
  • • Stainless steel flatware and dinnerware
  • • Hand and measuring tools

Non-compliance penalties (DFARS 252.225-7012)

  • Replacement of non-compliant items at supplier's cost
  • Price reduction on delivered goods
  • Debarment from future DoD contracts

Pricing — supply rates differ from construction

What a $1M manufacturing supply bond actually costs

Supply bonds typically price below construction performance bonds because the risk profile is different: shorter contract terms, delivery-based completion triggers rather than multi-year construction default exposure, and (for Berry-compliant manufacturers) a more controllable supply chain. Rate ranges below reflect carrier appetite on annual supply bonds in the $250K–$5M penal range.

The SBA path — how small manufacturers bond a DoD contract

The SBA Surety Bond Guarantee Program (15 U.S.C. 694b) is the most reliable route for manufacturers without three years of audited financials or significant working capital. SBA stands behind the carrier, the carrier writes the bond, the manufacturer keeps the contract.

$9M
General contract cap

Bid, performance, payment, and ancillary bonds on commercial and most federal contracts. Cap effective March 18, 2024 (raised from $6.5M).

$14M
Federal contract cap

Available when the federal contracting officer certifies the SBA guarantee is necessary for the small business to obtain bonding. Raised from $10M on the same March 2024 rule.

$500K
Quick Bond simplified application

Streamlined SBA QuickApp underwriting for contracts up to $500,000 — the fastest path for first-time small-manufacturer applicants.

FY2025 program record: $10.6 billion in total contract value guaranteed (a 15% jump over FY2024), with 75 bonds specifically guaranteed for manufacturers and fabricators — a 36% increase year over year. SBA Administrator Kelly Loeffler attributed program growth to small manufacturers meeting new DoD and DLA demands. Source: SBA Office of Surety Guarantees.

From the producer's desk

What manufacturers actually run into when the bond clause lands

Three patterns repeat in our intake calls from manufacturers who just won a DoD or DLA award. First, the bond clause arrives without a stated trigger — the contracting officer cites FAR 52.228-16 in the contract but does not name which FAR 28.103-2 condition is in play. We ask, in writing, every time. Naming the trigger determines whether the penal sum needs to equal the full contract value or whether a reduced penal sum tied only to the advance payment amount will satisfy the agency (contracting officers have discretion under FAR Part 28 on penal sum for supply bonds). On a $4M supply contract with $800K in advances, that distinction is the difference between a $40,000 annual premium and an $8,000 one at the same rate.

Second, the Berry Amendment documentation problem hits late. A manufacturer wins a textile or food-item DLA contract, signs the DFARS 252.225-7012 clause without fully mapping their supplier list against 10 U.S.C. 4862 coverage, and realizes mid-production that one input is offshore. Replacement, price reduction, or in the worst case debarment exposure follows — and the bond claim conversation starts with the surety. The right move is at solicitation review: pull every covered article on the BOM, match each one to a U.S.-source supplier with mill certs, and have the certification package ready before award.

Third, DLA Office of Counsel legal review under DLAD 28.106-90 surprises first-time DLA contractors. Civilian-agency bonds clear underwriting and get on the contracting officer's desk in 48 hours. DLA adds an internal legal-sufficiency review on every bond and every consent of surety — days, sometimes a full week, of additional processing. Manufacturers who timed their production start against the civilian-agency cadence lose schedule. The fix is building DLA timelines into the production schedule from day one, not from the bond approval date.

Eric Drummond

Licensed Surety Producer (license pending)

1 years of surety bond experience
State Licenses:
  • Nevada: License #Pending issuance (All Bond Lines)

Verify licenses at your state insurance department

Specialty Areas:
Manufacturing Supply BondsDLA & DoD Contract BondingBerry Amendment ComplianceSBA Surety Bond Guarantee Program
Professional Certifications:
  • Surety bond producer training (NASBP coursework)

All content is researched from official state and federal sources (.gov) and reviewed by surety bond specialists. We maintain direct integrations with Treasury-certified surety carriers rated A- or better by AM Best.

Manufacturing & supply bond questions our intake desk hears most

Six questions answered from the FAR/DFARS/DLAD text, not from generic surety marketing copy. If your question is not here, the producer's direct line is below.

My DLA contracting officer just asked for a performance bond on a $1.8M MRE supply contract. Why — supply contracts are not supposed to need one?
FAR 28.103-1(a) is your starting point: agencies shall not generally require performance and payment bonds for other than construction contracts. The bond is only on the table because one of the four FAR 28.103-2 triggers fired. On DLA prime vendor and long-term agreements, it is almost always trigger #3 — substantial progress payments before delivery of end items starts. DLA advances cash to manufacturers to fund raw material buys for ration packs, uniforms, hardware kits, and similar production runs; that advance creates the government exposure FAR 28.103-2(3) is designed to cover. Ask the CO to point to the specific 28.103-2 trigger in writing — it determines whether the bond is mandatory or contracting officer discretion, and whether you can negotiate a reduced penal sum with the contracting officer (FAR Part 28 permits agency discretion on penal sum for supply bonds).
Does the Miller Act apply to my manufacturing contract — and is the threshold $100,000 or $150,000?
Neither, if you are a pure manufacturer delivering goods. The Miller Act (40 U.S.C. 3131) applies only to contracts 'for the construction, alteration, or repair of any public building or public work of the Federal Government.' The statutory threshold in 40 U.S.C. 3131(a) is $100,000. The $150,000 figure that competitor pages cite is sourced from 10 U.S.C. 2852, which substitutes $150,000 for $100,000 — but only for military construction and military family housing projects, not supply contracts. Manufacturing/supply contracts fall under FAR 28.103, which is permissive (trigger-based) rather than mandatory. The two regulatory branches almost never get cited correctly side-by-side.
What is the difference between Standard Form 25 and Standard Form 1418, and which one does my DoD supply contract use?
SF 25 (performance bond) and SF 25A (payment bond) are construction forms under FAR 52.228-15. SF 1418 (performance bond) and SF 1416 (payment bond) are non-construction forms under FAR 52.228-16. A DoD or DLA supply contract — even a multi-million dollar manufacturing run — uses SF 1418 and SF 1416, not SF 25. This is not a clerical detail: the clauses behind each form set different default penal sums, different remedies, and different relationships to advance payment protection. Carriers underwriting a manufacturing supply bond expect SF 1418 paperwork; the wrong form on the desk slows underwriting and sometimes fails legal sufficiency review under DLAD 28.106-90.
How does Berry Amendment compliance actually affect bond underwriting — or is that just marketing?
It is real, and it favors the manufacturer. DFARS 252.225-7012 (Preference for Certain Domestic Commodities, APR 2022 revision) implements 10 U.S.C. 4862 — the Berry Amendment, renumbered from 10 U.S.C. 2533a by Public Law 116-283, the FY2021 NDAA, effective January 1, 2022. A Berry-compliant manufacturer has documented, all-domestic sourcing for textiles, clothing, food items, tents, natural fibers, flatware, and similar covered articles. From a surety's underwriting perspective, that documented domestic supply chain materially reduces the contract's delivery-disruption risk — no offshore raw material sourcing, no foreign port chokepoints, no FX exposure. That lower-risk profile shows up in the rate the carrier can quote. Specialty metals (titanium, tantalum, etc.) are a separate statute — 10 U.S.C. 4863 — and a separate DFARS clause (252.225-7009).
I am a small manufacturer with two years of operating history. Can the SBA help me bond a $4M DoD contract I just won?
Yes — that is exactly what the SBA Surety Bond Guarantee Program is designed for. Effective March 18, 2024, the program guarantees bid, performance, payment, and ancillary bonds up to $9 million for general contracts and up to $14 million for federal contracts when the contracting officer certifies that the SBA guarantee is necessary for the small business to obtain bonding. The SBA QuickApp simplified process is available for contracts up to $500,000. In FY2025 the program guaranteed 75 bonds specifically for manufacturers and fabricators — a 36% jump over FY2024, driven by demand from small DoD and DLA suppliers. The path: produce the contract award, line up an SBA-participating surety, submit the underwriting package with the SBA guarantee request running in parallel.
What about cost-plus DoD contracts — do they need a performance bond?
DFARS 228.102-1 waives the performance and payment bond requirement entirely for cost-reimbursement contracts. If your DoD contract is structured as cost-plus (cost-plus-fixed-fee, cost-plus-incentive-fee, etc.), no FAR 28.103-2 trigger analysis is needed — the bond requirement is off the table by DoD-wide regulation. Watch for one wrinkle: if a cost-type prime contract includes fixed-price construction subcontracts over $40,000, the prime must require payment protection from those subs ($40,001–$150,000) or full payment + performance bonds ($150,000+) per the same DFARS section. That subcontractor protection rule is one of the more frequently missed items in DoD subcontract management.

Authoritative sources

Every factual claim on this page traces back to one of the following. We link with nofollow to preserve internal link equity — click through to verify the regulatory text.

FAR Subpart 28.1 — Bonds and Other Financial Protections

The core federal rule. FAR 28.103-1(a) makes bonds permissive on supply contracts; 28.103-2 enumerates the four trigger conditions; 28.103-3 makes payment bonds derivative.

FAR 52.228-16 — Performance and Payment Bonds (Other Than Construction)

The clause that goes in your supply contract when FAR 28.103-2 triggers. Requires SF 1418 (performance) and SF 1416 (payment) in CO-determined adequate amounts.

DFARS 252.225-7012 — Preference for Certain Domestic Commodities

The Berry Amendment implementing clause (APR 2022). Implements 10 U.S.C. 4862, prescribed by DFARS 225.7002-3. Required in DoD solicitations and contracts including FAR Part 12 commercial items.

SBA Surety Bond Guarantee Program

Current caps: $9M general / $14M federal (effective March 18, 2024). QuickApp simplified process available for contracts up to $500,000. Statutory authority 15 U.S.C. 694b.

10 U.S.C. 4862 — Berry Amendment (current codification)

Renumbered from 10 U.S.C. 2533a by Public Law 116-283 (FY2021 NDAA), effective January 1, 2022. Defines covered domestic-source articles.

Treasury Circular 570 — Approved Surety Companies (T-List)

Federal supply contract bonds must be written by T-listed sureties (31 U.S.C. 9304–9308; FAR 28.202). The list is published annually by the Bureau of the Fiscal Service.

Send the solicitation

Most manufacturing bond questions are answered by reading FAR 28.103-2 against the specific CLIN and advance-payment structure of the actual contract. Send us the solicitation or the award. We will identify the trigger condition, confirm whether SF 1418 / SF 1416 is required, size the penal sum against the advance amount, and pull T-listed carrier quotes scoped to your Berry compliance position — usually within one business day.