Need a bid bond? Free to request. No obligation.
Get a quoteBid Bond Cost by State — 2026 Guide
Public-works bid security follows one rule almost everywhere: a percentage of the bid amount — federal floor at 20% (capped at $3 million), state DOTs typically at 5–10%, municipalities commonly 10%. The surprising part is the premium math behind that percentage.
The percentage that controls state and local bid bonds
5% – 10%
Typically the state and local range, as a share of the contractor’s bid amount. FAR 28.101-2 sets the 20% federal floor (capped at $3 million); state procurement codes vary: TxDOT and FDOT set the amount in each proposal form or advertisement, Caltrans requires at least 10% on its contracts (§2-1.34), and most large municipalities typically spec 10%. FAR 28.101-2 and the TxDOT, FDOT and Caltrans specifications read November 6, 2026; other agency figures not re-checked since May 2026.
- Amount: Typically 5%-10% of the contractor's bid amount on state and local work (20% federal floor, capped at $3 million, under FAR 28.101-2; TxDOT and FDOT set it per proposal; at least 10% on Caltrans contracts; typically 10% at most large municipalities).
- Typical cost (estimate): Often $0 with a performance commitment (some carriers charge a $50-$200 filing fee on federal jobs); major-municipality bonds $100-$300 flat or rated 0.5%-1%. The surety sets the final price.
What the bid bond actually costs — three real-world scenarios
Each row applies the procurement code’s required percentage to a representative bid, then shows the typical bid-bond premium. “Bid bond cost” is not a single number — percentage flexes by code, and premium is often $0 against a backed performance commitment.
Federal $5M construction
FAR 28.101-2 sets a bid guarantee of at least 20% (capped at $3 million) — a $1,000,000 bid bond. With the same surety on the performance/payment bonds, premium is typically $0; some carriers charge a $50–$200 filing fee.
State DOT $2M highway
$100 – $300
At a 5% guaranty (an example; TxDOT and FDOT set the amount in each proposal form or advertisement), that is a $100,000 bid bond. Caltrans requires at least 10% on its contracts (at least $200,000) under Caltrans Standard Specifications 2026, §2-1.34. Premium typically $100–$300 flat or free against the performance commitment.
Municipal school $750K
$75 – $150
School-district RFPs commonly spec 10% — a $75,000 bid bond. Smaller bonds are flat-fee priced ($75–$150); many carriers waive the fee for prequalified GCs.
Citations: FAR 28.101-2 (acquisition.gov); TxDOT Std Specs Item 2 §2.8.2; FDOT Std Specs §2-7; Caltrans Std Specs §2-1.34. Numbers illustrate the documented bid-process pattern, not specific carrier quotes. FAR 28.101-2 and the TxDOT, FDOT and Caltrans specifications read November 6, 2026.
Bid bond cost has two distinct meanings. The bond amount is a percentage of the contractor’s bid — at least 20% (capped at $3 million) on federal projects under FAR 28.101-2, typically 5% or 10% on state DOT work, as the solicitation sets it, and typically 10% on municipal RFPs. The premium — what the contractor actually pays the surety — is usually $0 to a few hundred dollars when the same carrier is writing the performance and payment bonds, because the bid bond is treated as a sunk cost of acquiring the bonded project. Standalone bid bonds (no performance commitment) are typically quoted at $100–$300 flat for small bonds, or 0.5%–1% of bond amount on larger ones.
FAR 28.101-2 (acquisition.gov) and the TxDOT, FDOT and Caltrans specifications read November 6, 2026; other agency figures not re-checked since May 2026; Treasury Circular 570 surety listings verified May 2026.
Federal construction is governed by FAR 28.101. Subpart 28.101-1 requires a bid guarantee whenever a performance bond is required — meaning every federal construction project at or above the simplified acquisition threshold falls under the Miller Act bond requirements framework. The bid guarantee is at least 20% of the bid price, capped at $3 million. Acceptable forms: surety bid bond from a Treasury Circular 570 listed surety, certified/cashier’s check, or U.S. Treasury bonds. Bid bonds are just one piece; our hub covers all contractor bond types so you can see where this one fits.
State DOT contracts follow each agency’s standard specifications. TxDOT Std Specs Item 2 §2.8.2 and FDOT Std Specs §2-7 set the guaranty amount in each project’s proposal form or advertisement. Caltrans requires bidder’s security of at least 10 percent of the bid on its contracts (Caltrans Standard Specifications 2026, §2-1.34).
Municipal and school-district RFPs set the percentage in the procurement document itself. Most specify 5% or 10% bid security; neither is universal. Always verify the procurement document — the spec controls regardless of any generic rule. The bid bonds hub covers submission mechanics; the bid bond cost page drills into rate-vs-amount math.
Bid Bond Percentage by Procurement Tier — Federal, State DOT, Municipal
FAR from acquisition.gov; TxDOT, FDOT and Caltrans specifications read November 6, 2026; other agency rows not re-checked since May 2026
| Procurement Tier | Bid % of Bid Amount | Source / Citation | Premium Pricing Pattern |
|---|---|---|---|
| Federal construction (FAR 28.101) | At least 20% (max $3 million) | FAR 28.101-2 (acquisition.gov) | Free w/ performance commitment; $50–$200 filing |
| Miller Act federal | At least 20% (max $3 million) | 40 USC § 3131; FAR 28.101-2 | Free w/ performance commitment |
| TxDOT (Texas highway) | Set per proposal form | TxDOT Std Specs Item 2 §2.8.2 | Free w/ performance commitment |
| FDOT (Florida DOT) | Set per advertisement | FDOT Std Specs §2-7 | Free w/ performance commitment |
| Caltrans (California DOT) | At least 10% (Caltrans contracts) | Caltrans Standard Specifications 2026, §2-1.34 | Free w/ performance commitment |
| NYSDOT (New York DOT) | 5% | NYSDOT Std Specs §102-08 | Free w/ performance commitment |
| PennDOT (Pennsylvania DOT) | 10% | PennDOT Pub. 408 §102.07 | Free w/ performance commitment |
| IDOT (Illinois DOT) | 5% (≥ $10M); 10% spec common | IDOT Std Specs Article 102.09 | Free w/ performance commitment |
| MassDOT | 5% | MassDOT Std Specs §1.04 | Free w/ performance commitment |
| ODOT (Oregon DOT) | 10% | ODOT Std Specs 00130.40 | Free w/ performance commitment |
| Other state DOTs | Typically 5%–10% | State DOT standard specifications | Free w/ performance commitment |
| Major-municipality public works | 10% (most common) | Municipal procurement code | $100–$300 flat OR rated 0.5%–1% |
| School district RFPs | Typically 5%–10% | District-specific RFP | $75–$300 flat |
| Federal design-build | At least 20% of proposed price (max $3 million) | FAR 36.6; FAR 28.101-2 | Free w/ performance commitment |
| Subcontractor bid bonds (private) | Typically 5%–10% (per GC) | GC’s bid form | $100–$500 flat or rated |
TxDOT and FDOT set the amount in each proposal form or advertisement, and Caltrans sets at least 10% on its contracts (specifications read November 6, 2026); other agency rows not re-checked since May 2026. Federal percentages are FAR-controlled. Municipal RFPs vary; the percentage in your specific solicitation controls.
Sources: FAR Part 28 (acquisition.gov); TxDOT, FDOT and Caltrans specifications read November 6, 2026; other agency rows not re-checked since May 2026; Treasury Circular 570 (TreasuryDirect.gov), verified May 2026.
Standalone Bid Bond Premium — When Carriers Actually Charge
Based on a $500,000 (5% of $10M bid) bond amount
- Excellent (740+)Rate: 0.40% – 0.60%$2,000 – $3,000
- Very Good (700–739)Rate: 0.50% – 0.75%$2,500 – $3,750
- Good (650–699)Rate: 0.75% – 1.0%$3,750 – $5,000
- Fair (600–649)Rate: 1.0% – 1.5%$5,000 – $7,500
- Poor (550–599)Rate: 1.5% – 2.5%$7,500 – $12,500
- Subprime (<550)Rate: 2.5%+ or decline$12,500+
Credit-tier rate bands apply only when the bid bond is rated standalone (no performance commitment). For most prequalified contractors writing the bid through a surety program, some carriers provide the bid bond at little or no cost; the carrier decides. Underwriting weighs working capital, bondable backlog, and contractor experience more heavily than personal credit on commercial surety lines.
Bid bonds are the one surety product on the construction line where a $0 premium is the dominant pricing pattern. The documented bid-process pattern shows industry standard surety underwriting treating the bid bond as a sunk cost of acquiring the performance bond and payment bond business that follows if the contractor wins. Performance and payment bonds carry the actual premium — typically 0.5%–3% of contract price under most carrier filings — while some carriers provide the bid bond at little or no cost.
- Bid-to-award ratios drive the economics. Industry standard ratios run 4:1 to 6:1 bids-to-awards. A surety underwriting one $5M federal bid produces zero direct premium; the same surety writing the awarded $5M performance/payment bond at 1.5% produces $75,000. Charging little or nothing for the bid bond can make sense on those numbers.
- Prequalification — not transaction underwriting — is the gate. A contractor approved under a surety facility for a $10M single job and $30M aggregate gets bid bonds submitted promptly, free, against any project sized inside that envelope. State procurement codes require the bid bond itself to be issued by a Treasury-listed surety; the prequalification machinery sits behind that.
- Four scenarios flip the bid bond to rated. First, the contractor is shopping bid-only with no performance commitment from the same surety — carrier charges $100–$500 flat or 0.5%–1% rated. Second, project size sits outside the contractor’s approved limits. Third, project class is outside carrier appetite (specialty work, environmental remediation, first-time design-build). Fourth, expedited issuance inside 24–48 hours triggers rush fees of $50–$200.
- Underwriting elements reviewed even on a low-cost bid bond. Working capital ratio, bondable backlog, tangible net worth, contractor experience by class of work, and project-specific fit. The bid bond costs nothing in dollars, but the prequalification work — CPA-prepared financials, work-in-progress schedule, references — is real. The bid bond requirements guide covers prequalification in depth.
Sources: Surety & Fidelity Association of America (SFAA) market commentary; Treasury Circular 570 listing mechanics; FAR 52.228-1(b) acceptable bond forms. Mechanics described are general to the industry-standard surety construction line.
Pricing mode
Free / nominal filing
Estimated bid-bond premium
$0 – $200
Carriers commonly waive the bid-bond premium when the same surety has approved the contractor for the awarded performance/payment bond. Filing fees of $0–$200 are common when charged at all.
Get Your Exact Bid Bond Price
Estimated premium: $0 – $200 — an agent follows up with carrier pricing for your project
No cost until your bond is issued | No Obligation | 2 Minutes
BuySuretyBonds Insurance Agency · CA Lic. #6019861 — Mainline Holdings LLC dba BuySuretyBonds.com
Estimates are illustrative. Final premium is set by the underwriting surety at time of application and varies by credit, experience, state, and carrier.
What happens next
- Send your details. It takes about 2 minutes and costs nothing.
- A licensed agent reviews your request and submits it to our carriers.
- You get exact pricing from the carrier. Most quotes come back within one business day.
- Pay only when your bond is issued. No obligation to buy.
Estimates use FAR 28.101-2 + state DOT spec percentages, current as of May 2026. Final premium is set by the underwriting surety based on the contractor’s qualification, working capital, bondability, and the carrier’s appetite for the project size and class of work.
- Find the bid solicitation’s bond clause. For federal projects, look for the FAR 52.228-1 (or 52.228-15) clause and the Standard Form 24 bid bond template referenced under FAR 28.106-1(a). For state DOT contracts, the bond clause sits in the agency’s standard specifications (TxDOT Item 2 §2.8.2; FDOT §2-7; Caltrans Standard Specifications 2026, §2-1.34). For municipal RFPs, it’s in the procurement document itself, usually the “Instructions to Bidders” section.
- Confirm the bond percentage. Federal floor is 20% of bid amount (capped at $3 million); TxDOT and FDOT set it in the proposal form or advertisement; Caltrans requires at least 10% on its contracts. Municipal and school RFPs commonly use 10%. Multiply the bond percentage by your planned bid to get the bond face amount.
- Ask the surety whether it charges for the bid bond against the performance commitment. If the same carrier is writing the awaiting performance and payment bond inside an approved bonded program, some carriers provide the bid bond at little or no cost. Ask explicitly — some smaller carriers charge filing fees even inside facility programs.
- Pull the quote from a Treasury-listed surety. Federal procurement requires the surety to appear on Treasury Circular 570. Most state DOTs require the same. The Treasury list publishes each surety’s underwriting limitation — the maximum single-bond size the carrier can issue without co-surety.
Bid bond vs performance bond — cost difference?
Some carriers provide bid bonds at little or no cost against an awaited performance commitment; performance bonds are rated at 0.5%–3% of contract price. See the performance bond vs bid bond comparison for the full mechanics.
Is “bid security” the same as a bid bond?
Bid security is the umbrella category — surety bid bond, cashier’s check, certified check, irrevocable letter of credit, U.S. Treasury bonds. A bid bond is the surety-issued form that doesn’t tie up cash. FAR 52.228-1(b) and state DOT specs accept any of these.
When do bid bonds carry a charge?
Some carriers charge little or nothing for bid bonds when the same surety has pre-qualified the contractor under a bonded program. Carriers charge $50–$200 filing on rush issuance, $100–$500 flat on standalone bid-only orders, or 0.5%–1% of bond amount on large standalone bonds.
How is the bid bond sized on cost-plus or design-build?
Sized against the offeror’s proposed price ceiling or GMP — not a hypothetical lump sum. FAR 36.6 federal design-build still applies FAR 28.101-2’s 20% minimum (capped at $3 million) to the proposed total. State design-build statutes (Florida F.S. § 287.05712) follow the same logic.
Federal vs state percentage — which wins?
It depends on who runs the letting. Federal procurements under FAR 28.101-2(b) require a bid guarantee of at least 20% of the bid price, capped at $3 million. State-run lettings follow the state specification instead: Caltrans requires bidder’s security of at least 10 percent of the bid on its contracts (Caltrans Standard Specifications 2026, §2-1.34), while TxDOT and FDOT set the amount in each project’s proposal form or advertisement (TxDOT Item 2 §2.8.2; FDOT §2-7). Read the bond clause in the solicitation, because that document controls the percentage.
What happens on bid-bond default?
Obligee draws on the bid bond up to the penal sum — typically the difference between the defaulting bid and the next-lowest responsive bid, capped at face amount (5% or 10% of original bid). The surety pays the obligee and pursues the contractor under the indemnity agreement.
Related reading: the bid bond requirements guide covers submission mechanics; the performance bond requirements guide covers what follows on award; the Miller Act bond requirements page covers the federal construction framework; sibling cost guides: performance bond cost, court bond cost, probate bond cost.
RFP bid-bond checklist — before you submit
Run this five-item checklist against the procurement document. If every line clears, the bid bond is ready to file with the bid package.
- Bond percentage confirmed — pulled from the solicitation’s “Instructions to Bidders” (federal: FAR 52.228-1; state DOT: standard specs; municipal: RFP body).
- Surety is Treasury Circular 570 listed — with single-bond underwriting limitation at or above the bid bond face amount.
- Bond form matches the solicitation — SF 24 for federal; agency-specific forms for state DOT (TxDOT Form 2042-A; FDOT’s Form 525-040-43; Caltrans CEM-2002).
- Premium pricing confirmed — $0 against performance commitment, or flat fee / rated for standalone. Verified May 2026.
- Power of attorney attached — current dated POA from the surety, notarized, with seal. Required by every public obligee.
Treasury-listed surety carriers. No cost until your bond is issued.
Bid bond in hand before the bid window closes
Some carriers provide bid bonds at little or no cost for qualified accounts — but that still requires a Treasury-listed surety to run the prequalification. If you're bidding a federal, state DOT, or municipal job and need a bid bond before the submission deadline, the form below starts the process. The same surety that issues your bid bond will write the performance bond and payment bond if you win, which is why the bid bond itself may cost little or nothing; the carrier decides.
For overall cost context across bond types, see the surety bond cost guide.