Bid Bond CalculatorPenal Sum + Premium, Federal and Private
Every bid bond has two numbers. The penal sum is the face value the obligee can collect against — 20% of the bid on federal work per FAR 28.101-2, or 5–10% on state and private work. The premium is what you pay the surety — almost always $0 inside an approved bonding program.
Enter your bid below and pick a percentage. The math comes from a FAR 28.101-2 reading and state Little Miller Act statutes, not a marketing guess. For the next bond in the trinity, use the performance bond calculator and payment bond calculator. For the product background, see bid bonds and the bid bond requirements guide.
Run the Numbers
Our underwriter tells you the exact penal sum the obligee requires and confirms bonding-line capacity before you submit your bid.
The Penal Sum Is a Percentage of the Bid
Bid bonds are the only contract-surety product where the face amount is a function of the bid itself. Performance and payment bonds key off the final contract price — bid bonds key off what you offered to do the work for. Three common percentages, one formula.
Bid Bond Penal Sum Formula
Federal floor: FAR 28.101-2(a)(1) — 'at least 20% of the bid price but not to exceed $3 million.' State/private default: 5–10% depending on solicitation language and state Little Miller Act.
Federal (Miller Act)
20%
Of bid price, capped at $3M. Applies to federal construction contracts that in turn require P&P bonds (Miller Act triggers at $150,000 per 40 USC §3132).
State / Municipal
5%–10%
Varies by state Little Miller Act. California Public Contract Code §10167 uses 10%; Texas Government Code §2253 and Florida §255.05 commonly run 5%.
Private / AIA A310
5%–10%
Owner dictates in the solicitation. AIA Document A310 defaults to 5% of the bid; some private owners mirror Miller Act and require 20%.
Miller Act Bid Bond: The 20% Rule, Spelled Out
Every federal construction contract above the Miller Act threshold needs three bonds — bid (on the bidding side), then performance and payment (on the awarded side). The bid bond rule is the one contractors miss most often because the percentage is unusually high and the statute is spread across two sources.
Official Federal (FAR / Miller Act) Requirements
"A bid guarantee shall be in an amount equal to at least 20 percent of the bid price but not to exceed $3 million."Federal Acquisition Regulation • FAR 28.101-2(a)(1)
Threshold trigger
The bid bond requirement is a downstream consequence of needing a performance/payment bond. 40 USC §3131 requires P&P bonds on federal construction contracts over $150,000, which means bid bonds attach to the same job. Service contracts and supply contracts generally do not need a Miller Act bid bond unless the solicitation calls for one under FAR 28.103.
The $3M cap
FAR 28.101-2(a)(1) caps the bid guaranty at $3,000,000 regardless of bid size. A contractor bidding a $50M federal job does not post a $10M bid bond — they post $3M. The contracting officer can override this cap in writing but it is uncommon. The cap prevents mid-size contractors from being locked out of large federal work purely by bonding capacity.
The Treasury-Certified Surety Requirement
Federal bid bonds must be written by a surety listed in Treasury Circular 570 — the authorized surety list maintained by the Department of the Treasury, Fiscal Service. The contracting officer will reject a bid bond written by a non-listed carrier, which means your bid is non-responsive. Every surety in our program is Circular 570 listed with single-project capacity sized to Miller Act jobs.
Little Miller Act Bid Bond Percentages (State Public Works)
Every state has a public-works bonding statute modeled on the federal Miller Act. Most landed around 5% for the bid bond; a handful run 10%. Always read the specific solicitation — an individual agency can require more than the statutory floor.
| State | Bid Bond % | Statute | Notes |
|---|---|---|---|
| California | 10% | Pub Cont Code §10167 | State-funded public works; bid security required for bids over $25K. |
| Texas | 5% | Gov Code §2253 | State/local public works; governmental body may require more. |
| Florida | 5% | §255.05 | Public works over $200K local / $100K state (exemption thresholds). |
| New York | 5% | State Finance §137 | Also requires performance and payment bonds on state contracts. |
| Illinois | 10% | 30 ILCS 550 | Bond Act of 1931; applies to state/municipal construction. |
| Ohio | 10% | ORC §153.54 | Public improvement projects; bid guaranty required. |
| Pennsylvania | 10% | 62 Pa.C.S. §903 | Procurement Code; bid security for state public works. |
| Georgia | 5% | OCGA §13-10-40 | State/local public works; 100% P&P on award. |
Percentages confirmed against each state legislature’s published statute as of April 2026. Individual solicitations may set a higher figure; always follow the bid package over the baseline statute.
Forfeiture: What the Penal Sum Actually Costs You
The penal sum is not theoretical. If you are the low bidder, win the award, and then fail to sign the contract or furnish the performance/payment bonds, the bid bond pays the obligee — and your surety comes to you for repayment under the indemnity agreement.
Federal (FAR 28.101-4)
The obligee’s measure of damages is the difference between your bid and the next-lowest responsive bid, capped at the penal sum. The surety pays the obligee. Then the surety invokes the General Indemnity Agreement to collect from the principal (and personal indemnitors).
Text: 40 USC §3131 + FAR 28.101-4
Worked scenario
You bid $2M on a federal job. 20% bid bond = $400K penal sum. You win, then discover your subs overpromised and you cannot deliver. The second-lowest bid was $2.35M. The government collects $350K from the surety. You owe the surety $350K plus fees — the $400K penal sum was just the ceiling.
Lesson: every bid bond is real exposure. Never bid work you cannot bond-back.
Alternative bid guarantees
FAR 28.101-1 allows contractors to post bid security as a certified check, cashier’s check, bank draft, postal money order, or U.S. bonds/notes instead of a surety bond. Almost no one does this on large work. A $3M bid at 20% ties up $600K in cash for the full bid-evaluation window — working capital that could fund three or four simultaneous bids if posted as surety bonds instead.
The only scenario where cash makes sense: a contractor who cannot qualify for any bonding line at all. If that is you, the SBA Surety Bond Guarantee Program guarantees sureties up to $9M so they can back otherwise-unbondable small contractors.
If You Do Not Have a Bonding Program: Standalone Pricing
Contractors without an approved bonding line can still get a bid bond, but the pricing changes. A standalone bid bond is underwritten as a one-off rather than part of a program, and the surety charges a small premium because there is no guaranteed P&P bond on the other side.
Standalone Bid Bond Premium by Credit Tier
Based on a $500,000 penal sum bond amount
- 720+ (Excellent)Rate: 0.5% or $250 flat$250
- 680–719 (Very Good)Rate: 0.75% or $400 flat$400
- 640–679 (Good)Rate: 1.0% or $500 flat$500
- 600–639 (Fair)Rate: 1.5%$7,500
- Below 600Rate: 2–3%$10,000–$15,000
Standalone bid bonds on one-off jobs. Premium drops to $0 once an approved bonding program is in place. Figures reflect typical market rates for contract surety on a $500K penal sum; actual pricing depends on credit, financial strength, WIP, and obligee history.
Bonding program
$0
Bid bonds issue at no premium. Surety earns on the P&P bond when you win. Requires underwriting up front (WIP, financials, GIA), then unlimited bid bonds within program limits.
Standalone / one-off
$100–$500+
Flat fee on smaller penal sums, 1–3% on larger. Use for one-time bids when you do not plan to bond more public work. Same-day issuance on clean credit.
Bid due this week?
Our underwriting desk issues electronic bid bonds same-day on approved lines and turns standalone one-offs in 2–4 hours for clean credit. Call 1-844-810-BOND (2663) or start online below.
After the Bid: The Rest of the Contract Surety Trinity
The bid bond gets you to the award. These are the bonds that execute the work and pay the subs.
Performance Bond Calculator
100% of contract price, rate-based premium. Required when you convert the winning bid into an active contract.
Run the mathPayment Bond Calculator
Protects subcontractors and suppliers. On federal jobs, the same Treasury-listed surety must write both P&P bonds — they are usually issued as a pair.
Run the mathConstruction Bond Calculator
All three bonds priced together as a program. Use this when you want the bid / performance / payment trinity quoted as a unit.
Run the mathBid Bond Questions Contractors Actually Ask
Answers verified against FAR, 40 USC §3131, and state Little Miller Act statutes.
Does the Miller Act really require a 20% bid bond on every federal job?
+
Why do sureties hand out bid bonds with no premium?
+
What happens if I win the bid but refuse the job?
+
Is the bid bond amount the same as the cost to me?
+
Can I use a certified check or cashier’s check instead of a bid bond?
+
Do I need to be approved for a bonding program before I bid?
+
Post Your Bid Bond Without Tying Up Working Capital
Every surety in our program is listed on Treasury Circular 570. Same-day electronic bid bonds, $0 premium inside an approved program, Miller Act capacity up to the $3M federal cap and well beyond on state/private work.
All content is researched from official state and federal sources (.gov) and verified before publication. BuySuretyBonds.com works with Treasury-certified, A- minimum rated surety carriers serving all 50 states.