Need a bid bond? Free to request. No obligation.
Get a quoteBid Bond Calculator
Penal Sum + Premium, Federal and Private
This bid bond cost calculator returns the two numbers every bid bond has. The penal sum is the face value the obligee can collect against — 20% of the bid on federal work per FAR 28.101-2, or typically 5–10% on state and private work. The premium is what you pay the surety — almost always $0 inside an approved bonding program. Public bidding usually also assumes you already hold the contractor license bond your state requires to bid in the first place.
Enter your bid below and pick a percentage. The math comes from a FAR 28.101-2 reading and state agency specifications, not a marketing guess. For the next bond in the trinity, use the performance bond calculator and payment bond calculator. For the product background, see bid bonds and the bid bond requirements guide.
- Who requires it: The project owner. Federal work follows FAR 28.101-2.
- Amount: 20% of the bid on federal work (not to exceed $3 million), typically 5-10% on state and private work.
- Typical cost (estimate): Often $0 inside a bonding program, or $100-$500 flat for a standalone bid bond. The surety sets the final price.
- Timing: We submit complete applications to the carrier promptly; most quotes within one business day.
Run the Numbers
Send the bid documents: an agent reviews the penal sum the obligee requires and the information the carrier needs before your bid date.
The Penal Sum Is a Percentage of the Bid
Bid bonds are the only contract-surety product where the face amount is a function of the bid itself. Performance and payment bonds key off the final contract price — bid bonds key off what you offered to do the work for. Three common percentages, one formula.
Bid Bond Penal Sum Formula
Federal floor: FAR 28.101-2(b) — 'at least 20 percent of the bid price but shall not exceed $3 million.' State/private default: typically 5–10% depending on the solicitation and the agency's rules.
Federal (FAR 28.101-2(b))
20%
Of bid price, capped at $3M. Applies to federal construction contracts that in turn require P&P bonds (Miller Act triggers at $150,000 per 40 USC §3132).
State / Municipal
Typically 5%–10%
Varies by agency and solicitation, typically 5–10%. Caltrans requires at least 10% on its contracts; TxDOT and FDOT set it in each proposal form or advertisement.
Private / AIA A310
Dollar amount on form
On AIA Document A310, the bond amount is written on the form as a dollar figure. Separately, on private jobs it is commonly 5% to 10% of the bid, and some private owners mirror the FAR 28.101-2(b) floor and require 20%.
Miller Act Jobs: The FAR 28.101-2(b) 20% Bid Bond Rule, Spelled Out
Every federal construction contract above the Miller Act threshold needs three bonds — bid (on the bidding side), then performance and payment (on the awarded side). The bid bond rule is the one contractors miss most often because the percentage is unusually high and the statute is spread across two sources.
Official Federal (FAR 28.101-2(b)) Requirements
"The bid guarantee amount shall be at least 20 percent of the bid price but shall not exceed $3 million."Federal Acquisition Regulation • FAR 28.101-2(b)
Threshold trigger
The bid bond requirement is a downstream consequence of needing a performance and payment bond. 40 USC §3131 requires P&P bonds on federal construction contracts over $150,000, which means bid bonds attach to the same job. Service contracts and supply contracts generally do not need a Miller Act bid bond unless the solicitation calls for one under FAR 28.103.
The $3M cap
FAR 28.101-2(b) caps the bid guaranty at $3,000,000 regardless of bid size. A contractor bidding a $50M federal job does not post a $10M bid bond — they post $3M. The cap prevents mid-size contractors from being locked out of large federal work purely by bonding capacity.
The Treasury-Listed Surety Requirement
Federal bid bonds must be written by a surety listed in Treasury Circular 570 — the authorized surety list maintained by the Department of the Treasury, Fiscal Service. The contracting officer will reject a bid bond written by a non-listed carrier, which means your bid is non-responsive. Every surety in our program is Circular 570 listed with single-project capacity sized to Miller Act jobs.
State Bid Security Rules (State Public Works)
Little Miller Acts are payment and performance bond statutes. The bid security amount comes from the agency’s rules or the solicitation itself, typically 5% to 10% of the bid. Always read the specific solicitation — an individual agency can require more.
| State | Bid Bond % | Source | Notes |
|---|---|---|---|
| California | At least 10% (Caltrans contracts) | Caltrans Std Specs 2026 §2-1.34 | Caltrans contracts; other California agencies typically 10%, set per solicitation. |
| Texas | Set per proposal form (TxDOT) | TxDOT Std Specs Item 2 §2.8.2 | TxDOT lettings; other agencies: see the solicitation. |
| Florida | Set per advertisement (FDOT) | FDOT Std Specs §2-7 | §255.05 is Florida’s payment and performance bond statute (generally required on public works contracts over $100K; smaller contracts may be exempt). |
| New York | Set per solicitation | State Finance §137 (payment bond) | §137 requires payment bonds on public contracts; it sets no bid percentage. |
| Illinois | Typically 10%; set per solicitation | — | 30 ILCS 550 not fetched; follow the bid package. |
| Ohio | Bond: full bid; check/LOC: 10% | ORC §153.54 | State and political subdivisions (not ODOT); surety liability capped at the lesser of the bid difference or 10% of the bond. |
| Pennsylvania | Typically 10%; set per solicitation | — | 62 Pa.C.S. §903 not fetched; follow the bid package. |
| Georgia | Typically 5%; set per solicitation | — | OCGA §13-10-40 not fetched; follow the bid package. |
Ohio R.C. 153.54, Florida §255.05 and New York State Finance §137, plus the TxDOT, FDOT and Caltrans specifications, were read from official sources on November 6–7, 2026; other rows not re-checked since April 2026. Individual solicitations may set a higher figure; always follow the bid package.
Forfeiture: What the Penal Sum Actually Costs You
The penal sum is not theoretical. If you are the low bidder, win the award, and then fail to sign the contract or furnish the performance/payment bonds, the bid bond pays the obligee — and your surety comes to you for repayment under the indemnity agreement.
Federal (FAR 52.228-1(d)–(e))
If the contract is terminated for default, you are liable for any cost of acquiring the work that exceeds the amount of your bid, and the bid guarantee is available to offset the difference. If the surety pays, it invokes the General Indemnity Agreement to collect from the principal (and personal indemnitors).
Text: FAR 52.228-1(d)–(e)
Worked scenario
You bid $2M on a federal job. 20% bid bond = $400K penal sum. You win, then fail to sign the contract documents or furnish the bonds within 10 days after receiving the forms, and the contract is terminated for default. Re-acquiring the work costs the government $2.35M, which is $350K more than your bid; the $400K bid guarantee is available to offset that $350K. If the surety pays it, you owe the surety $350K plus fees.
Lesson: every bid bond is real exposure. Never bid work you cannot bond-back.
Alternative bid guarantees
FAR 52.228-1(b) allows contractors to post bid security as a certified check, cashier’s check, irrevocable letter of credit, postal money order, or U.S. bonds/notes instead of a surety bond. Almost no one does this on large work. A $3M bid at 20% ties up $600K in cash for the full bid-evaluation window — working capital that could fund three or four simultaneous bids if posted as surety bonds instead.
The only scenario where cash makes sense: a contractor who cannot qualify for any bonding line at all. If that is you, the SBA Surety Bond Guarantee Program guarantees sureties up to $9M so they can back otherwise-unbondable small contractors.
If You Do Not Have a Bonding Program: Standalone Pricing
Contractors without an approved bonding line can still get a bid bond, but the pricing changes. A standalone bid bond is underwritten as a one-off rather than part of a program, and the surety charges a small premium because there is no guaranteed P&P bond on the other side.
Standalone Bid Bond Premium by Credit Tier
Based on a $500,000 penal sum bond amount
- 720+ (Excellent)Rate: 0.5% or $250 flat$250
- 680–719 (Very Good)Rate: 0.75% or $400 flat$400
- 640–679 (Good)Rate: 1.0% or $500 flat$500
- 600–639 (Fair)Rate: 1.5%$7,500
- Below 600Rate: 2–3%$10,000–$15,000
Standalone bid bonds on one-off jobs. Premium drops to $0 once an approved bonding program is in place. Figures reflect typical market rates for contract surety on a $500K penal sum; actual pricing depends on credit, financial strength, WIP, and obligee history.
Bonding program
Low / none
Some carriers charge little or nothing for bid bonds. Surety earns on the P&P bond when you win. Requires underwriting up front (WIP, financials, GIA), then unlimited bid bonds within program limits.
Standalone / one-off
$100–$500+
Flat fee on smaller penal sums, 1–3% on larger. Use for one-time bids when you do not plan to bond more public work. Issuance depends on carrier underwriting.
Bid due this week?
Tell us your bid date up front. Timing depends on the carrier's underwriting and how quickly the bid documents and financial information are provided. Call 1-844-810-BOND (2663) or start online below.
After the Bid: The Rest of the Contract Surety Trinity
The bid bond gets you to the award. These are the bonds that execute the work and pay the subs.
Performance Bond Calculator
100% of contract price, rate-based premium. Required when you convert the winning bid into an active contract.
Run the mathPayment Bond Calculator
Protects subcontractors and suppliers. On federal jobs, the same Treasury-listed surety must write both P&P bonds — they are usually issued as a pair.
Run the mathConstruction Bond Calculator
All three bonds priced together as a program. Use this when you want the bid / performance / payment trinity quoted as a unit.
Run the mathBid Bond Questions Contractors Actually Ask
Answers cite FAR, 40 USC §3131, and state agency specifications.
Does FAR 28.101-2(b) really require a 20% bid bond on every federal job?
+
Why do sureties hand out bid bonds with no premium?
+
What happens if I win the bid but refuse the job?
+
Is the bid bond amount the same as the cost to me?
+
Can I use a certified check or cashier’s check instead of a bid bond?
+
Do I need to be approved for a bonding program before I bid?
+
Post Your Bid Bond Without Tying Up Working Capital
Every surety in our program is listed on Treasury Circular 570. Bid bonds can carry no separate premium inside an approved bonding program; carrier underwriting sets the program and its limits.
All content is researched from official state and federal sources (.gov). BuySuretyBonds.com works with Treasury-listed surety carriers.