Missouri Performance BondMo. Rev. Stat. § 107.170

Bond threshold: $50,000.

Missouri's $50,000 trigger is lower than the federal Miller Act's $150,000; state and local jobs are bonded at a smaller size than federal ones.

Prompt Submission
Pay Only When Issued
Quick answer
Missouri's Little Miller Act (Mo. Rev. Stat. § 107.170) requires performance and payment bonds on covered public works contracts. The trigger: $50,000. Any cost here is an estimate; the surety sets the final price.
  • Who requires it: Missouri public owners awarding covered public works contracts (Mo. Rev. Stat. § 107.170).
  • Typical cost (estimate): about $500-$1,000 on a $50,000 contract with excellent credit, up to $2,500-$5,000 below 620. The surety sets the final price.
  • Timing: We submit complete applications to the carrier promptly; most quotes within one business day.
Get a Missouri performance bond quote

Missouri public works bonding at a glance

Bond threshold
$50,000
Controlling statute
Mo. Rev. Stat. § 107.170
Claim notice (sub-tier claimants)
Only 'remote suppliers' must give notice: a remote supplier (any material supplier having a contract with a second- or lower-tier subcontractor, or with another material supplier of any tier) is not entitled to recover on the bond unless it has given written notice to the contractor that it has not been paid within 90 days of the time it last supplied materials on the project (§107.170.2). The sections cited prescribe no method of service. They set no notice requirement for subcontractors (at any tier), laborers, or suppliers to first-tier subcontractors, and no preliminary-notice requirement. Also, furnishing a §107.170 bond bars mechanic's liens by subcontractors/suppliers (§107.170.8).
Federal jobs in Missouri
Miller Act (40 U.S.C. § 3131): bonds on federal contracts over $150,000

Source: Mo. Rev. Stat. § 107.170 and the sources cited below.

For license bonds and every other bond a contractor may need, start with our hub: Bonds for contractors.

Getting paid: Missouri payment bond claims

On Missouri public work, Mo. Rev. Stat. § 107.170 (with § 522.300 on suit on the bond) makes the payment bond, not a lien on public property, the security for unpaid labor and materials.

Notice

Only 'remote suppliers' must give notice: a remote supplier (any material supplier having a contract with a second- or lower-tier subcontractor, or with another material supplier of any tier) is not entitled to recover on the bond unless it has given written notice to the contractor that it has not been paid within 90 days of the time it last supplied materials on the project (§107.170.2). The sections cited prescribe no method of service. They set no notice requirement for subcontractors (at any tier), laborers, or suppliers to first-tier subcontractors, and no preliminary-notice requirement. Also, furnishing a §107.170 bond bars mechanic's liens by subcontractors/suppliers (§107.170.8).

Sources: source 1, source 2, source 3. General information, not legal advice.

What a Missouri performance bond costs

Premium on a $50,000 Missouri contract (the trigger size):

How to get bonded for public work in Missouri

Bid bond at bidding, performance and payment bonds at award: required on contracts over $50,000 under Mo. Rev. Stat. § 107.170.

Missouri performance bond questions

Does Missouri require a performance bond on public projects?

Yes, on covered public works contracts (Mo. Rev. Stat. § 107.170). The trigger: $50,000. Owners, lenders and bid documents can also require one by contract.

What is the Missouri Little Miller Act threshold?

$50,000.

How much does a performance bond cost in Missouri?

On a $50,000 Missouri contract, typical ranges run about $500-$1,000 for excellent credit up to $2,500-$5,000 below 620. The issuing carrier sets the final price.

Do subcontractors have to give notice before a Missouri payment bond claim?

Only 'remote suppliers' must give notice: a remote supplier (any material supplier having a contract with a second- or lower-tier subcontractor, or with another material supplier of any tier) is not entitled to recover on the bond unless it has given written notice to the contractor that it has not been paid within 90 days of the time it last supplied materials on the project (§107.170.2). The sections cited prescribe no method of service. They set no notice requirement for subcontractors (at any tier), laborers, or suppliers to first-tier subcontractors, and no preliminary-notice requirement. Also, furnishing a §107.170 bond bars mechanic's liens by subcontractors/suppliers (§107.170.8). See Mo. Rev. Stat. § 107.170 (with § 522.300 on suit on the bond).

How do I get a Missouri performance bond?

Use the form on this page with the contract amount and the public owner.

What happens after I apply for a performance bond in Missouri?

The carrier decides approval and the final premium; you pay only when the bonds are issued.

Eric Drummond, Licensed Surety Producer
Reviewed by
Eric Drummond, Licensed Surety Producer

All content is researched from official state and federal sources (.gov). BuySuretyBonds.com works with Treasury-listed surety carriers.

Bidding a Missouri public job?

No payment until your bond is issued.

Get a Missouri performance bond quote
CallSe habla españolGet Free Quote